Material Shortages Crippling US Grid Expansion and Supply Chains

3 min readSources: National Law Review

Critical material shortages are causing years-long delays in US grid equipment production.

Why it matters: Legal and regulatory professionals in energy and infrastructure must anticipate challenges tied to long lead times and supply constraints affecting project timelines and compliance.

  • Edison Electric Institute members plan $208 billion investment in 2025, up 49% from 2020.
  • Lead times for power transformers average 128 weeks; generator transformers 144 weeks, per Wood Mackenzie.
  • Power-transformer prices rose 77% since 2019; demand for generator step-up transformers increased 274%.
  • US relies heavily on imports for essential minerals like grain-oriented electrical steel (GOES).

The US electrical grid is facing significant material bottlenecks amid plans for modernization and expansion. Investment by Edison Electric Institute member companies is projected to reach nearly $208 billion in 2025, up nearly 49 percent from about $139.8 billion in 2020. However, demand for critical materials has outpaced supply, resulting in sharp increases in cost and excessive delays.

According to industry analysis, lead times for power transformers now average 128 weeks (over two years), while the larger generator step-up transformers average 144 weeks. Prices for these lifesaving components have surged 77 percent since 2019, and demand for generator transformers has climbed 274 percent in that period. This is primarily due to limited availability of specialized materials such as grain-oriented electrical steel (GOES), which the U.S. Geological Survey confirms is mostly imported, as domestic production is lacking.

The Department of Energy highlights that supply chain challenges include dependence on imports, limited domestic manufacturing capacity, and complex customization requirements, stretching lead times for crucial equipment like transformers and circuit breakers to two or more years (DOE report).

Moreover, a study from the National Laboratory of the Rockies points out that although domestic supplies of copper and aluminum appear sufficient to support grid expansion, diverting these exclusively to grid projects would constrain other industries' production (academic study).

Chris Rogers, a supply chain analyst, emphasizes this shift: "Supply chain risk in late 2026 is shifting from purely geographic chokepoints toward scarce materials, constrained components and compressed decision time." These bottlenecks suggest material scarcity, not just funding, is now the primary grid expansion hurdle.

For legal and compliance teams, these constraints will impact contract negotiations, project timelines, risk management, and regulatory compliance. Addressing the complexities tied to imported materials and extended failure risks requires close regulatory scrutiny and proactive corporate strategies.

By the numbers:

  • $208 billion — projected grid investment in 2025, a 49% increase since 2020
  • 128 weeks — average lead time for power transformers as of Q2 2025
  • 274% — growth in demand for generator step-up transformers since 2019

Yes, but: While domestic copper and aluminum supplies seem adequate for grid needs, prioritizing them here could limit other sectors' production, complicating supply allocation.